March 2005
– The left photo shows the completed masonry
veneer of the kitchen and gym outer walls. On the right is the stud
framing for the administrative office area.
|
 |
 |
January 2005
– The second floor structural framing and
masonry walls are shown on the left. On the right is the structure of
the gym roof.
|
 |
 |
November 2004
– On the left, load bearing masonry is being
erected for the classroom wing. On the right preparations are
beginning to pour the gym floor.
|
 |
 |
September 2004
– An underground fire water main and adjacent
domestic water (drinking water) main are being installed. On the right
looking northeast, the library masonry is being installed. The
gymnasium block work is in the background.
|
 |
 |
|
August 2004
– Construction work begins with clearing the
site and stockpiling topsoil. In the photo on the right, workers are
pouring a concrete footer for an exterior masonry wall on the south
one-story building. |