September
2004
–
The left photo show the classroom layout with the cabinetry and
bookshelves. On the right is storage space for use by kindergarten students.
|
 |
 |
August
2004
–
The left photo shows the brick finish on the outside of the east
side of the classroom wing just north of the mechanical yard. In the
photo on the right, carpenters are installing the cabinetry in a
classroom where students will put their backpacks, lunch boxes and
extra items during the day.
|
 |
 |
June 2004
–
The photo on the left shows the outer walls of the Clinic on the north
side of the building. The photo on the right is a first-floor
classroom that has been drywalled.
|
 |
 |
May 2004
– On the
left is an interior view of the computer room as the walls go
up. On the right is a western view of the main entrance on the north
side of the building.
|
 |
 |
April
2004
–
The photo on the left is looking from the roof to the south classroom
area. The right photo shows the north stairwell in the B area
prior to concrete installation.
|
 |
 |
March
2004
–
On the left is an interior photo looking from the Reading area to the
reception area, prior to interior wall installation. On the right is
a view of the north elevation looking from the 3rd floor to the future
clinic. Old Rockdale School is in the background.
|
 |
 |
February
2004
–
Work is beginning on the interior of the dining area looking east
towards the kitchen and the west elevation of the third-floor
classroom area.
|
 |
 |
January
2004
– The
steel structure is being built for the third-floor classroom wing. The
first-floor corridor south of the dining area is taking shape.
|
 |
 |
December
2003
– In
the clinic area more work is being done on the foundation while
masonry work continues on the second-floor classroom wing.
|
 |
 |
November
2003
– Work is
beginning on the first- floor mechanical room and its major equipment
(left),
as well as the first-floor restroom group piping (right), prior to the masonry
walls being installed.
|
 |
 |
Late October
2003
– Steel
framing is being erected above the kitchen/dining area. Construction
is beginning on the second-floor level of a classroom area.
|
 |
 |
Mid-October
2003
– Walls
forming the corridor leading to a classroom area are erected and
earthwork is being done under where the clinic will be housed.
|
 |
 |
Early October
2003
– Progress
continues on the masonry walls in the classroom wing while steel beams
are erected in the kitchen area of the new school site.
|
 |
 |
September
2003
– Masonry
walls go up in the south classroom area of the new Rockdale Academy.
|
 |
 |
August
2003
–
Installation of the underground plumbing and concrete foundations for
the south classroom section of Rockdale Academy continues while the
outline of the new school's classroom wing takes shape. The current
Rockdale Academy can be seen in the background in the photo on the
right.
|
 |
 |
July 2003
– Workers prepare the east side of the site for completion of concrete
retaining walls and build temporary roads to allow construction
equipment to move around the site.
|
 |
 |
Late June 2003
– Earthwork continues on the eastern side of the site as the building's
shape, or footprint, is laid out and covered with gravel.
|
 |
 |
June 2003
– The storm-water retention tank nears completion, as site work
continues at the new Rockdale Academy site.
|
 |
 |
Late May
2003 – Excavation for the new storm-water retention tank is
complete. Crews recently poured the tank's concrete bottom. The tank
is located under what will be the school's new entrance driveway off
Northern Avenue.
|
 |
 |
Early May 2003
– Work progresses along the new concrete retaining walls on the site's
east and south property lines.
|
 |
 |
April 2003 –
Shovels dig a large hole to make room for new storm-water pipes, and
concrete foundations are put into place for several retaining walls
along the sides of the property.
|
 |
 |
March 2003
–
Work crews grade, level and prepare the former Condon School site
before construction begins on the new Rockdale school.
|
 |
 |
January 2003
–
A cleared, level site
awaits construction to begin on the new 84,000-square-foot school,
which will hold 650 students in kindergarten through eighth grade.
|
 |
 |
December 2002
–
Work
continues at the site to remove debris and level the area.
|
 |
 |
November 2002
–
Work crews clear debris
from the former Condon School site.
|