<% Option Explicit 'You must dim all variables before using them. Response.Buffer = True 'Hold web pages on the server until they are done Response.Expires = 0 'Since this site is entirely data driven, web pages should expire as soon as they are created. On Error Resume Next 'Declare all variables. Dim strSQL Dim dataconn Dim rsHighSchools Dim rsSatelliteSchools Dim rsElemSchools Dim strOutput Dim strGrades Dim strBegGrade Dim strEndGrade Dim strInterim Dim strCounter Dim strTimes '---- CursorTypeEnum Values ---- Const adOpenForwardOnly = 0 Const adOpenKeyset = 1 Const adOpenDynamic = 2 Const adOpenStatic = 3 '---- LockTypeEnum Values ---- Const adLockReadOnly = 1 Const adLockPessimistic = 2 Const adLockOptimistic = 3 Const adLockBatchOptimistic = 4 '---- CursorLocationEnum Values ---- Const adUseNone = 1 Const adUseServer = 2 Const adUseClient = 3 Const adUseClientBatch = 3 'Get connection to database Set dataconn = Server.CreateObject("ADODB.Connection") dataconn.ConnectionString ="PROVIDER=MSDASQL;DRIVER={SQL Server};SERVER=198.203.127.110;DATABASE=theMap;UID=web_visitor;PWD=web_visitor;" dataconn.Open %> Schools Title Page



Athletic Facilities

Stargel Stadium
Groundbreaking
Dedication

 

Click on an image to get additional information about that particular school:

This goes to a page outlining the Facilities Master Plan recommendation for the school.

This links to simple floor plans for the school.

This link will show construction or renovation in progress.

This goes to a page on the Ohio School Facilities Commission (OSFC) web site with more detailed information on this particular school such as bid deadlines, contacts and additional photos.

<% '-----------------------------------ELEMENTARY SCHOOLS--------------------------------------- %>


Opened
(In order of opening)
 

Rockdale
New Construction/Existing Site

(Avondale, 335 Rockdale Ave) Construction completed on a 86,160-square-foot school for 650 students in grades K-8. The new school is built on the site of the district's former Condon School. Students moved into new building on January 3, 2005. Dedication and ribbon-cutting ceremony was January 13, 2005.
     Opening Day
     Dedication
     Architect: GBBN Architects Inc. + WA Inc.
     Building Construction Cost: $13,985,500
     Total Project Cost (includes such things as site preparation, demolition): $16,789,056
Midway
New Construction/New Site

(Westwood, 3156 Glenmore Ave.) Construction completed on a 76,800-square-foot school for 550 students in grades K-8 in August 2005. Students moved into new building in August 2005. Dedication and ribbon-cutting ceremony was September 2, 2005.
     Architect: Voorhis, Slone, Welsh, Crossland Architects Inc.
     Building Construction Cost: $13,356,490
    
Total Project Cost (includes such things as site preparation, demolition): $18,414,380
Roll Hill
New Construction/Existing Site

(North Fairmount, 2411 Baltimore) Construction completed on a 84,000-square-foot school for 650 students in grades K-8. Old school building demolished December 2003-January 2004. Students moved into new building August 2005. Dedication and ribbon-cutting ceremony was October 6, 2005.
     Architect: Roth Partnership/Lesko Associates
     Building Construction Cost: $11,047,765
    
Total Project Cost (includes such things as site preparation, demolition): $12,978,126
Winton Hills
New Construction

(Winton Place, 5300 Winneste Ave.) Construction completed on a 66,001-square-foot school for 450 students in grades K-8. Students moved into new building August 2005. Dedication and ribbon-cutting ceremony was September 15, 2005.
     Architect: BHDP Architecture
     Building Construction Cost: $10,118,220
    
Total Project Cost (includes such things as site preparation, demolition): $11,718,497
Pleasant Hill
New Construction/Existing Site

(College Hill, 1350 W. North Bend Rd) Construction completed on a 84,000-square-foot school for 650 students in grades K-8. Students moved into new building in November  2005. Dedication and ribbon-cutting ceremony was held October 20, 2005.
     Architect: Burgess & Niple Limited
     Building Construction Cost: $10,624,974
    
Total Project Cost (includes such things as site preparation, demolition): $13,176,469
Riverview East Academy
New Construction/New Site

(Columbia Tusculum, 3555 Kellogg Ave) Construction completed on a 105,000-square-foot school for 615 students in grades K-12. Students moved into the new building on January 3, 2006. The dedication and ribbon-cutting ceremony was held on January 12, 2006.
     Architect: SFA Architects Inc. + Alexander Camabean & Associates
     Building Construction Cost: $17,653,73
    
Total Project Cost (includes such things as site preparation, demolition): $22,705,869
Woodward High School
New Construction/Existing Site

(Bond Hill, 7005 Reading Rd) Construction completed on a 261,870-square-foot school for 1,200 students with three wings designed for three career-technical programs. This is CPS’ first new high school building since 1962. Students moved into the new building as of the first day of the 2006-07 school year, on August 22, 2006. The dedication and ribbon-cutting ceremony was held on September 15, 2006.
     Architect: Steed Hammond Paul + DH Architects
     Building Construction Cost: $40,053,392
    
Total Project Cost (includes such things as site preparation, demolition): $47,765,066
Cheviot
Renovation

(Cheviot, 4040 Harrison Ave) Construction completed on a 74,000-square-feet school for 550 students. The addition was finished in November 2005. Students moved into the newly renovated building as of the first day of the 2006-07 school year, on August 22, 2006. The dedication and ribbon-cutting ceremony was held on November 2, 2006.
     Architect: Glaserworks
     Building Construction Cost: $13,621,960
    
Total Project Cost (includes such things as site preparation, demolition): $16,396,797
Rees E. Price School
New Construction/New Site (Whittier Annex)

(Price Hill, 1228 Considine Avenue) Construction completed on an 84,000-square-foot school for 650 students as the new home for former Whittier School beginning August 2006.
     Architect: McGill Smith Punshon Inc. and DeJong
     Building Construction Cost: $11,238,552
    
Total Project Cost (includes such things as site preparation, demolition): $13,211,769
Ethel M. Taylor Academy (formerly Millvale)
New Construction/New Site

(Millvale, 1930 Fricke Road) Construction completed on a 66,100-square-foot school for 450 students. The building opened for students on January 3, 2007. The dedication and ribbon-cutting ceremony was held on February 1, 2007.
     Architect: URS Corp.
     Building Construction Cost: $10,516,014
    
Total Project Cost (includes such things as site preparation, demolition): $13,675,543
Shroder
New Construction/New Site (Eastwood)

(Madisonville, 5030 Duck Creek Rd) Construction completed on a 98,000-square-foot school for 600 students. The building opened for students on January 3, 2007. The dedication and ribbon-cutting ceremony was held in March 2007.
    
Architect: Voorhis, Slone, Welsh, Crossland Architects Inc.
     Building Construction Cost: $15,070,987
    
Total Project Cost (includes such things as site preparation, demolition): $17,858,907
Withrow High School
Renovation

(Hyde Park) Withrow University moved into renovated north wings over Spring Break 2007. Withrow International moved into renovated south wings in April 2006. Gymnasium, kitchen and cafeteria completed the renovation in Fall 2006. Demolition of vocational building, renovation of stadium and completion of site work finished in August 2007.
     Architect: Cole+Russell and Fanning/Howey
     Building Construction Cost: $38,539,594
    
Total Project Cost (includes such things as site preparation, demolition): $43,145,719
Roberts
New Construction/Existing Site

(Price Hill) Construction completed on the 95,000-square-foot school for 750 students. Building opened for students in August 2007. The dedication and ribbon-cutting ceremony was held in October 2007.
    
Architect: McGill Smith Punshon Inc. and DeJong
     Building Construction Cost: $16,146,347
    
Total Project Cost (includes such things as site preparation, demolition): $17,368,405
Douglass
New Construction/New Site

(Walnut Hills) Construction completed on 74,000-square-foot school for 550 students. Building opened for students in August 2007. The dedication and ribbon-cutting ceremony was held in May 15, 2008.
    
Architect: DNK Architects + DH Architects
     Building Construction Cost: $13,078,725
    
Total Project Cost (includes such things as site preparation, demolition): $15,992,681
Hays-Porter
New Construction/Existing Site

(West End, 1030 Cutter Street) Construction completed on 66,100 square-foot school for 450 students. Building opened for students in August 2007.
     Architect: Moody-Nolan Inc.

    
Building Construction Cost: $12,807,775
    
Total Project Cost (includes such things as site preparation, demolition): $15,153,247
Academy of World Languages
New Construction/Existing Site

(Evanston) Construction completed on 84,144-square-foot school for 650 students. Building opened for students in December 2007. The dedication and ribbon-cutting ceremony was held in January 2008.
     Architect: McGill Smith Punshon Inc.
     Building Construction Cost: $14,881,079
   
 Total Project Cost (includes such things as site preparation, demolition): $14,917,705
Bond Hill
New Construction/Existing Site

(Bond Hill) — Construction completed on 66,100-square-foot school for 450 students. Demolition of old building completed Summer 2006. New building opened for students in March 2008. The dedication and ribbon-cutting ceremony was held in May 2008.
     Architect: Steed Hammond Paul + DH Architects
     Building Construction Cost: $12,754,244
    
Total Project Cost (includes such things as site preparation, demolition): $14,658,562
Mt. Airy
New Construction/Existing Site

(Mt. Airy) — Construction completed on 84,144-square-foot school for 650 students. Demolition of old building completed Fall 2006. New building opened for students in March 2008. The dedication and ribbon-cutting ceremony was held in October 2008.
     Architect: DH Architects Inc.
     Building Construction Cost: $14,897,235
    
Total Project Cost (includes such things as site preparation, demolition): $15,553,928
Carson
New Construction/
Existing Site

(Price Hill) — Construction completed on a 75,310-square-foot school for 550 students on current campus. Front annex building demolished July 2006 to make space for new building.  Demolition of old two-story building began July 2008. New building opened for students August 2008.  The dedication and ribbon-cutting ceremony was held in May 2009.
     Architect: GBBN Architects Inc.
     Building Construction Cost: $14,858,023
    
Total Project Cost (includes such things as site preparation, demolition): $19,479,192
Fairview
New Construction/New Site

(Clifton) Construction completed on 84,144-square-foot school for 650 students on former site of Clifton School’s south building. Demolition of existing building completed January 2006. New building opened for students August 2008.  The dedication and ribbon-cutting ceremony was held in September 2008.
     Architect: Glaserworks
     Building Construction Cost: $14,156,805
    
Total Project Cost (includes such things as site preparation, demolition): $15,652,567
Kilgour
Renovation and Addition

(Mt. Lookout) — Construction completed on a 23,630-square-foot addition and a full renovation of existing building for 450 students. New building opened for students August 2008. The dedication and ribbon-cutting ceremony was held in September 2008.
     Architect: Champlin/Haupt Architects, Inc
     Building Construction Cost: $12,849,801
    
Total Project Cost (includes such things as site preparation, demolition): $12,250,975
South Avondale
New Construction/Existing Site

(Avondale) — Construction completed on 84,144-square-foot school for 650 students. Demolition of old building completed in January 2006. New building opened for students August 2008. The dedication and ribbon-cutting ceremony was held in October 2008.
     Architect: ATA Beilharz Architects
     Building Construction Cost: $15,242,385
    
Total Project Cost (includes such things as site preparation, demolition): $16,519,676
Pleasant Ridge Montessori
New Construction/Existing Site

(Pleasant Ridge) — Construction completed on 75,310-square-foot school for 550 students. Demolition of old building completed. New building opened for students August 2008. The dedication and ribbon-cutting ceremony was held in September 2008.
     Architect: SHP Leading Design
     Building Construction Cost: $18,410,447
    
Total Project Cost (includes such things as site preparation, demolition): $20,417,689
Roselawn Condon
Renovation

(Roselawn) — Phase I completed  February 2008 on the 550-student building. Phase II included new entrance and main office, and Phase III included work on the gym and a new art room. Renovated building opened for students August 2008. The dedication and ribbon-cutting ceremony was held in April 2009.
     Architect: ATA
Beilharz Architects
     Building Construction Cost:  $9,405,943
Covedale
New Construction/Existing Site

(Covedale) — Construction completed on a 66,100-square-foot school for 450 students. Demolition of old Covedale building completed Summer 2006. New building opened for students January 2009. The dedication and ribbon-cutting ceremony was held in May 2009.
     Architect: KZF Design
     Building Construction Cost: $12,925,357
Parker
New Construction/Existing Site

(Madisonville) — Construction completed on a 75,310-square-foot school for 550 students on Parker’s campus. New building opened for students August 2009.
     Architect: Voorhis, Slone, Welsh, Crossland Architects
     Building Construction Cost: $13,529,397

Opening Soon
All dates and costs are estimates.
(In anticipated order of completion.)

Dater Montessori
Renovation

(Westwood) —  Construction bids out Fall 2008. Students moved August 2007 into temporary home at 1700 Grand Avenue, Price Hill, while renovation under way on building with final size of 165,636 square feet for 650 students. Construction began December 2008; finishes Spring 2010.
     Architect: Glaserworks
     Bid Tabulations:  Building Packages
     Building Construction Cost: $17,426,888
School for Creative & Performing Arts and Schiel Primary School for Arts Enrichment (K-12)
New Construction/New Site

(Over-the-Rhine) — Construction under way on a 250,000-square-foot school for 1,350 students. Topping-out ceremony held September 2008. SCPA will combine in new building with Schiel Primary School for Arts Enrichment. Construction began Fall 2007; finishes Spring 2010.
    Fund-raising Campaign
    Architect: Cole+Russell, Fanning/Howey, Moody Nolan
    Bid Tabulations:  Building Packages
    Building Construction Cost: $54,751,533
    Total Project Cost (includes such things as site preparation, demolition): $70,431,261
Sands
New Construction/Existing Site

(Mt. Washington) — Construction under way on an 84,143-square-foot school for 650 students on Sands’ campus. School operating in existing building while new building under construction on front of campus. Old building to be demolished when new one completed. Construction began Fall 2008; finishes Summer 2010.
     Architect: SHP Leading Design
     Bid Tabulations:  Building Packages, Site Work
     Building Construction Cost: $12,252,637

Under Construction
All dates and costs are estimates.
(In anticipated order of completion.)

Academy of Multilingual Immersion Studies (AMIS)
New Construction/Existing Site

(Bond Hill) —  Construction bids out September 2008. Students moved August 2007 into temporary home at 7001 Reading Road, Bond Hill, until construction completed on a 63,032-square-foot school for 400 students. Demolition of existing building scheduled for Fall 2008. Construction began January 2009; finishes Summer 2010.
     Architect: GBBN Architects Inc.
     Bid Tabulations:  Building Packages
     Building Construction Cost: $11,977,688
Hughes Center
Renovation

(University Heights) — Construction under way on the renovation of Classical Building for final size of 290,873 square feet for 1,200 students. Students moved August 2008 into Professional Building and an annex at back of campus while renovation work is under way. The annex will be retained for future expansion. Construction began Summer 2008; finishes Summer 2010.
     Architect: Cole+Russell, Fanning/Howey, Moody Nolan
     Building Construction Cost: $39,733,115
College Hill
Renovation & Addition

 (College Hill)  —  Construction bids out Fall 2008. Students moved August 2008 into temporary home at 1402 W. North Bend Road, College Hill, while work under way on a 31,734-square-foot addition for a final building of 101,732 square feet for 550 students. Building construction began April 2009, finishes Summer 2010.
     Architect:  Moody Nolan, Inc.
     Building Construction Cost: $16,865,034
Hartwell
Renovation &Addition

 (Hartwell)  —  Construction bids out Fall 2008. Students moved August 2008 into temporary home at 125 W. North Bend Road, Carthage, while Hartwell building is renovated with a 7,000-square-foot addition (a gym) and final size of 84,100 square feet for 400 students.
Construction work began May 2009, finishes Summer 2010.

    
Architect:  Moody Nolan, Inc.
     Building Construction Cost: $13,594,351
North Avondale
New Construction/Existing Site

(Avondale) —  Students moved August 2008 into temporary home at 876 Glenwood Avenue, Avondale, until construction completed on 85,470-square-foot building for 650 students. Demolition of existing building occurred  February 2009. Construction began February 2009; finishes Summer 2010.
     Architect: Cole+Russell, Fanning/Howey, Moody Nolan
     Bid Tabulations:  Building Packages
     Building Construction Cost:  14,369,466
R. A. Taft High
New Construction/Existing Site

(West End) — Construction bids out September 2008. Design completed on 100,200-square-foot school for 600 students. Students moved January 2008 into temporary home at 2240 Baltimore Avenue, North Fairmount, until new building completed. Demolition of old Taft began August 2008. Building onstruction began April 2009; finishes Spring  2011.
     Architect: Voorhis, Slone, Welsh, Crossland Architects
     Bid Tabulations:  Environmental Remediation, Site Work & Demolition, Building Packages
     Building Construction Cost:  $18,868,839

Up Next
All dates and costs are estimates.
(In anticipated order of completion.)

<% 'get recordset of all elementary schools strSQL = "select School_Code, School_Name, Address, Zip_code, Phone_Number, FAX_Number, " & _ " Grades, Principal, Interim_Principal, Secretary, School_Times, Email, Map_File, SnapShot_Page, " & _ " School_Web_Site, Report_Card, Facilities_Plan, Program_Focus, " & _ " (case School_Code when '153' then 'Parker' when '310' then 'Bloom' else School_Name end) as School_Name_For_Alphabetizing from School_Data " & _ " where (Grades like '%03%' or Grades like '%06%' and School_Code <> 333) and (Display_in_SL = 1 or Display_in_SL is null)" & _ " order by School_Name_For_Alphabetizing " Set rsElemSchools = Server.CreateObject("ADODB.Recordset") rsElemSchools.ActiveConnection = dataconn rsElemSchools.CursorLocation = adUseServer rsElemSchools.CursorType = adOpenForwardOnly rsElemSchools.LockType = adLockReadOnly rsElemSchools.Source = strSQL rsElemSchools.Open If Not (rsElemSchools.BOF and rsElemSchools.EOF) Then Do Until rsElemSchools.EOF 'for each record found, show all the info from the database 'interpret the grdlevels string strBegGrade = Left(rsElemSchools.Fields("Grades"), 2) strEndGrade = Right(rsElemSchools.Fields("Grades"), 2) If Left(strBegGrade,1) = "P" or Left(strBegGrade,1) = "K" Then strBegGrade = "K" End If If Left(strBegGrade,1) = "0" Then strBegGrade = Right(strBegGrade, 1) End If If Left(strEndGrade,1) = "0" Then strEndGrade = Right(strEndGrade, 1) End If 'use the non-breaking tag so that the grade string is not interrupted between lines strGrades = "(" & strBegGrade & "-" & strEndGrade & ")" If strBegGrade = strEndGrade Then strGrades = "(" & strBegGrade & ")" End If 'interpret the interim principal indicator strInterim="" If rsElemSchools.Fields("Interim_Principal") = "True" Then strInterim = " (Interim)" End If strTimes = rsElemSchools.Fields("School_Times") 'format Windsor's school times If rsElemSchools.Fields("School_Code") = "197" Then strTimes = Left(rsElemSchools.Fields("School_Times"), InStr(rsElemSchools.Fields("School_Times"), "(W)")+3) strTimes = strTimes & "
          " & Right(rsElemSchools.Fields("School_Times"), (Len(rsElemSchools.Fields("School_Times")) - InStr(rsElemSchools.Fields("School_Times"), "(W)")-2)) End If 'format Clifton's school times If rsElemSchools.Fields("School_Code") = "117" Then strTimes = Left(rsElemSchools.Fields("School_Times"), InStr(rsElemSchools.Fields("School_Times"), "),")+2) strTimes = strTimes & "
          " & Right(rsElemSchools.Fields("School_Times"), (Len(rsElemSchools.Fields("School_Times")) - InStr(rsElemSchools.Fields("School_Times"), "),")-1)) End If 'format Whittier's school times If rsElemSchools.Fields("School_Code") = "196" Then strTimes = Left(rsElemSchools.Fields("School_Times"), InStr(rsElemSchools.Fields("School_Times"), "),")+2) strTimes = strTimes & "
          " & Right(rsElemSchools.Fields("School_Times"), (Len(rsElemSchools.Fields("School_Times")) - InStr(rsElemSchools.Fields("School_Times"), "),")-1)) End If strCounter = 0 i = 0 %> <% If rsElemSchools.Fields("Program_Focus") <> "" Then %> <%End If %> <% rsElemSchools.MoveNext Loop End If '-----------------------------------SECONDARY SCHOOLS--------------------------------------- %> <% 'get recordset of all high schools strSQL = "select School_Code, School_Name, Address, Zip_code, Phone_Number, FAX_Number, " & _ " Grades, Principal, Interim_Principal, Secretary, School_Times, Email, Map_File, SnapShot_Page, " & _ " School_Web_Site, Report_Card, Facilities_Plan, Program_Focus, " & _ " (case School_Code when '410' then 'Taft' else School_Name end) as School_Name_For_Alphabetizing from School_Data " & _ " where (Grades like '%09%' or Grades like '10%') and (Display_in_SL = 1 or Display_in_SL is null) " & _ " order by School_Name_For_Alphabetizing " Set rsHighSchools = Server.CreateObject("ADODB.Recordset") rsHighSchools.ActiveConnection = dataconn rsHighSchools.CursorLocation = adUseServer rsHighSchools.CursorType = adOpenForwardOnly rsHighSchools.LockType = adLockReadOnly rsHighSchools.Source = strSQL rsHighSchools.Open If Not (rsHighSchools.BOF and rsHighSchools.EOF) Then Do Until rsHighSchools.EOF 'for each record found, show all the info from the database 'interpret the grdlevels string strBegGrade = Left(rsHighSchools.Fields("Grades"), 2) strEndGrade = Right(rsHighSchools.Fields("Grades"), 2) If Left(strBegGrade,1) = "P" or Left(strBegGrade,1) = "K" Then strBegGrade = "K" End If If Left(strBegGrade,1) = "0" Then strBegGrade = Right(strBegGrade, 1) End If If Left(strEndGrade,1) = "0" Then strEndGrade = Right(strEndGrade, 1) End If 'use the non-breaking tag so that the grade string is not interrupted between lines strGrades = "(" & strBegGrade & "-" & strEndGrade & ")" If strBegGrade = strEndGrade Then strGrades = "(" & strBegGrade & ")" End If 'exception to grades for Virtual High School If rsHighSchools.Fields("School_Code") = 943 Then strGrades = "
(9th grade to Age 22)" End If 'interpret the interim principal indicator strInterim = "" If rsHighSchools.Fields("Interim_Principal") = "True" Then strInterim = " (Interim)" End If 'SCPA school times needs some formatting If rsHighSchools.Fields("School_Code") = 333 Then strTimes = Left(rsHighSchools.Fields("School_Times"), InStr(rsHighSchools.Fields("School_Times"), ")")) strTimes = strTimes & "
          " & Right(rsHighSchools.Fields("School_Times"), InStr(rsHighSchools.Fields("School_Times"), ")")+1) Else strTimes = rsHighSchools.Fields("School_Times") End If '9:00-4:00 (grades 4-8) 8:15-3:15 (grades 9-12) strCounter = 0 i = 0 %> <% If rsHighSchools.Fields("Program_Focus") <> "" Then %> <% End If %> <% rsHighSchools.MoveNext Loop End If '-----------------------------------SATELLITE SCHOOLS--------------------------------------- %> <% 'get recordset of all satellite schools strSQL = "select School_Code, School_Name, Address, Zip_code, Phone_Number, FAX_Number, " & _ " Grades, Principal, Interim_Principal, Secretary, School_Times, Email, Map_File, SnapShot_Page, " & _ " School_Web_Site, Report_Card, Facilities_Plan, Program_Focus " & _ " from School_Data " & _ " where Grades is null and (Display_in_SL = 1 or Display_in_SL is null) order by School_Name " Set rsSatelliteSchools = Server.CreateObject("ADODB.Recordset") rsSatelliteSchools.ActiveConnection = dataconn rsSatelliteSchools.CursorLocation = adUseServer rsSatelliteSchools.CursorType = adOpenForwardOnly rsSatelliteSchools.LockType = adLockReadOnly rsSatelliteSchools.Source = strSQL rsSatelliteSchools.Open If Not (rsSatelliteSchools.BOF and rsSatelliteSchools.EOF) Then Do Until rsSatelliteSchools.EOF 'for each record found, show all the info from the database 'interpret the interim principal indicator strInterim = "" If rsSatelliteSchools.Fields("Interim_Principal") = "True" Then strInterim = " (Interim)" End If strTimes = rsSatelliteSchools.Fields("School_Times") strCounter = 0 i = 0 %> <% If rsSatelliteSchools.Fields("Program_Focus") <> "" Then %> <% End If %> <% rsSatelliteSchools.MoveNext Loop End If %>
Hoffman-Parham
New Construction/New Site

(Evanston) —  Design approved for a 62,998-square-foot building for 450 students in a merged school on the Parham site. Parham students moved August 2008 into the Hoffman building, 3060 Durrell Avenue, Evanston, until construction finished. Demolition of Parham building scheduled for Summer 2009. Construction begins October 2009; finishes Spring  2011.
     Architect:  DH Architects, Inc
     Building Construction Cost: $11,669,783
Clark
New Construction/Existing Site

(Hyde Park) —  Students moved August 2007 to 5425 Winton Ridge Lane, Winton Hills, until construction completed on a 102,174-square-foot building for 600 students. Demolition of old building completed April 2009. Construction to begin Spring 1010..
     Architect: Glaserworks
     Bid Tabulations:  Demolition, Environmental Remediation
     Building Construction Cost: $18,098,865
Chase
New Construction/Existing Site

 (Northside) —  Students moved August 2007 into temporary home at 1710 Bruce Avenue, Northside, until construction completed on a 67,274-square-foot school for 450 students. Construction begins Spring  2010.
     Architect: Cole + Russell, Fanning/Howey, Moody Nolan
     Bid Tabulations:  Demolition
     Building Construction Cost:  12,443,638
Western Hills/Dater
Renovation

(Western Hills) — Students moving into temporary homes in 3 phases during Summer 2009 in modulars on site and in Dater High School basement. Construction scheduled to begin September 2009. Renovation scheduled to finish 2011 until construction complete on renovated schools for 1900 students.
     Architect: SFA Architects
     Building Construction Cost:  $51,716,341

Future Projects
All dates and costs are estimates.
(In alphabetical order.)

Aiken
New Construction/Existing Site

On November 27, 2006, the Board reduced the enrollment capacity of the school by 600 students in grades 7-12 for a total capacity of 1000 students. Students expected to move to temporary swing space Summer 2010.
     Architect: Voorhis, Slone, Welsh, Crossland Architects
     Building Construction Cost: $29,304,753
Mt. Washington
Renovation

On November 27, 2006, the Board increased the enrollment capacity of the renovated school by 50 students for total capacity of 400 students.
    Architect: Moody Nolan Inc.
    Building Construction Cost:  $14,894,869
Oyler
Renovation

Students will move to a temporary location in Summer 2010, when renovation begins on a school renovation for 650 students.
    Architect: Roth Partnership
Rothenberg
Renovation & Addition

(Over-the-Rhine) — Design under way for a renovated building for 550 students. Several lots purchased around existing school will enlarge campus for playground, green space and an 11,120 square-foot gymnasim. Students temporarily using building at 2120 Vine Street, Over-the-Rhine.
     Architect:
WA Architects Inc. & GBBN Architects Inc.
     Building Construction Cost: 16,907,400
Sayler Park
Renovation

On November 27, 2006, the Board reduced the enrollment capacity of the renovated school by 50 students, for a total capacity of 400 students. Students scheduled to move December 2009 into modulars on site while renovation is under way. Construction begins Spring  2010.
    Architect:  Roth Partnership
Silverton
New Construction/Existing Site

On November 27, 2006, the Board increased the enrollment capacity of the new school by 50 students for a total capacity of 400 students. Construction begins Fall 2010.
    Architect:  GBBN Architects Inc.
    Building Construction Cost:  $14,007,563
W. H. Taft Elementary
New Construction

On November 27, 2006, the Board reduced the enrollment capacity of the renovated school by 50 students for a total capacity of 400 students.
    Architect:  DH Architects
Walnut Hills
Renovation

 Renovation planned for a school with a capacity of 1900 students.
  Architect:  SHP Leading Design

West Side Montessori High School
Renovation of an Existing Site

(Undetermined)  —  Students moved August 2007 into their temporary home at the former Jacobs Center, 5425 Winton Ridge Lane. Location of permanent home to be determined. (On November 27, 2006, the Board removed a new building for the new Montessori high school  from the Facilities Master Plan.)
Westwood
Renovation

(Westwood) —  Design under way to renovate the building for 400 students. Students moved August 2007 into temporary home at 2601 Westwood Northern Blvd., Westwood. Construction begins Summer 2010.
     Architect: Roth Partnership
     Building Construction Cost: 14,433,731
Winton Montessori
New Construction/New Site

The Winton Montessori building on Winton Road (formerly Winton Place School) will close when the Montessori school moves into a new building on the Schwab School site on Beech Hill Avenue. The building on the Schwab site will be demolished before construction begins on new 75,000 square-foot Winton Montessori building built for 650 students.  Construction begins Fall 2010.
    Architects:  Cole+Russell, Fanning/Howey, Moody Nolan
    Building Construction Cost:  $16,639,331
Woodford
New Construction

A new building will be built for a capacity of 550 students. Construction begins Spring  2010.
    Architect:  GBBN Architects Inc.

Removed from Plan

Bloom
Discontinue Use

Bloom closed June 2006.
Burton
Removed from Plan

On November 27, 2006, the Board removed Burton  from the Facilities Master Plan. The school will close and students will be reassigned. Burton will close June 2008. 
Bramble
Discontinue Use

Bramble closed spring 2005. The building is now being used by Pleasant Ridge School until its new building is completed.
Central Fairmount
Removed from Plan

On November 27, 2006, the Board removed Central Fairmount  from the Facilities Master Plan. The school closed and students were reassigned.
Gamble
Removed from Plan

On November 27, 2006, the Board removed Gamble  from the Facilities Master Plan. The school closed and students were reassigned. The building is being used now as a temporary home of Westwood School while the Westwood building is being renovated.
Heberle
Removed from Plan

On November 27, 2006, the Board removed Heberle  from the Facilities Master Plan. The school closed and students were reassigned.
Hoffman/Parham School
New Construction/New Site

On November 27, 2006, the Board decided to consolidate  Hoffman and  Parham into one school, effective Summer 2008.  Students will attend school in the Hoffman building while a new school is constructed on the Parham site.
Hyde Park
Re
moved from Plan

On November 27, 2006, the Board removed Hyde Park from the Facilities Master Plan. Hyde Park School closed spring 2005. The Hyde Park building is being temporarily used by Mt. Washington School while its building is renovated.
Jacobs
Removed from Plan

On November 27, 2006, the Board removed the Jacobs building  from the Facilities Master Plan. (The school closed and students moved to the Aiken campus in August 2005.) The building is being temporarily used by Clark and West Side Montessori schools.
Losantiville
Discontinue Use

Losantiville closed spring 2005.
Military Academy
Removed from Plan

On November 27, 2006, the Board removed a new building for a military academy from the Facilities Master Plan.
Porter
Removed from Plan

On November 27, 2006, the Board removed Porter from the Facilities Master Plan. (Porter School merged with Hays in the fall of 2000 and was slated to be replaced with a new building. The original Porter building was demolished in 2004.)
Quebec Heights
Removed from Plan

On November 27, 2006, the Board removed Quebec Heights  from the Facilities Master Plan. The school will be closed and students will be reassigned. The date for closing has not been determined.
Schwab
New Construction/Existing Site

The new building will become the new home of Winton Montessori School. On November 27, 2006, the Board reduced the enrollment capacity of the new building by 100 students. (Schwab School will close Summer 2008 and students will be reassigned.)
Washington Park
Removed from Plan

On November 27, 2006, the Board removed Washington Park  from the Facilities Master Plan. The school closed and students were reassigned. The building was demolished Fall 2007.
     Bid Tabulation:  Demolition
West Side Montessori High School
Renovation of an Existing Site

(Undetermined)  —  Students moved August 2007 into their temporary home at the former Jacobs Center, 5425 Winton Ridge Lane. Location of permanent home to be determined. (On November 27, 2006, the Board removed a new building for the new Montessori high school  from the Facilities Master Plan.)
Whittier
Removed from Plan

On November 27, 2006, the Board removed a new building for Whittier  from the Facilities Master Plan. Students moved August 2006 into the new Rees E. Price School on Considine Avenue, Price Hill. The building was demolished January 2008.
     Bid Tabulation:  Demolition

9/2009